Ogle County Highway Department

Road Closures & Construction



Road Name:
Adeline Road
Township:
Maryland
Location: 1/3 mile north of IL Route 64 Road
Closure Date: August 13, 2008
Estimated Completion Date: September 30, 2008
Contractor: Moring Construction, McConnell, IL
Contract Value: $253,407.95
Improvements: Bridge Replacement

Road Name: Crane Grove Road
Township: Forreston
Location: 1/4 mile south of Prairie Dell Road
Closure Date: June 4, 2008; constructed under traffic
Completion Date: July 22, 2008
Contractor: Northwest Illinois Construction, LLC, Rock Falls, IL
Contract Value: $40,218.00
Improvements: Culvert extensions and slope modifications

Road Name: Edson Road
Township: Monroe / Cherry Valley  
Location: 1/2 mile west of East Line Road
Anticipated Closure Date: Postponed until 2009
Contractor: n/a
Contract Value: n/a
Improvements: Bridge pier repairs

Road Name: Flagg Road
Township: Taylor
Location: Lee County line to Lowden Road
Start Date: July 8, 2008; constructed under traffic
ompletion Date: July 27, 2008
Contractor: Northwest Illinois Construction, LLC, Rock Falls, IL
Contract Value: $217,823.75
Improvements: Hot-mix asphalt overlay

Road Name: Grange Road & miscellaneous streets in Deer Creek Subdivision
Township: Flagg
Location: Union Pacific Railroad to IL Route 38 & Deer Creek Subdivision off Fowler Road
Start Date: May 27, 2008; Constructed under traffic
Completion Date: June 14, 2008
Contractor: Rockford Blacktop Construction Co, Rockford, IL
Contract Value: $191,937.12
Improvements: Hot-mix asphalt overlay

Road Name: Freeport Road
Township: Forreston
Location: 500 feet north of Townline Road
Closure Date: May 6, 2008; Constructed under traffic
Completion Date: May 16, 2008
Anticipated Backfill Completion Date: Late August, 2008
Contractor: Schlicting & Sons Excavating, Inc, Rockford, IL
Contract Value: $25,386.40
Improvements: Culvert extension by the contractor; slope modifications by Ogle County forces

Road Name: Freeport Road
Township: Brookville, Forreston
Location: IL Route 64 to Townline Road
Anticipated Start Date: Postponed until 2009
Anticipated Culverts Completion Date: n/a
Anticipated Backfill Completion Date: n/a
Contractor: Ogle County forces
Contract Value: n/a
Improvements: Culvert extensions and slope modifications

Road Name: IL Route 64
Township: Oregon-Nashua 
Location: Hasting Avenue to Daysville Road
Start Date: May 27, 2008
Completion Date: July 3, 2008
Contractor: Ogle County Highway Department
Contract Value: n/a
Improvements: Ditch improvements in the city of Oregon

Road Name: Lanark Road
Township: Lincoln
Location: 500 feet east of Freeport Road
Closure Date: May 13, 2008
Culverts Completion Date: May 30, 2008
Anticipated Backfill Completion Date: Late August, 2008
Contractor: Schlicting & Sons Excavating, Inc, Rockford, IL
Contract Value: $50,830.60
Improvements: Culvert replacement by the contractor; slope modifications by Ogle County forces

Road Name: Lowden Road
Township: Oregon-Nashua
Location: 1/2 mile north of Lighthouse Road
Anticipated Closure Date: August 1, 2008
Anticipated Completion Date: September 12, 2008
Contractor: Moring Construction, McConnell, IL
Contract Value: $149,482.00
Improvements: Bridge replacement

Road Name: Lowden Road
Township: Oregon-Nashua
Location: Flagg Road to Lighthouse Road
Start Date: July 14, 2008; Constructed under traffic
Anticipated Culverts Completion Date: August 29, 2008
Anticipated Backfill Completion Date: Fall, 2008
Contractor: Northwest Illinois Construction, LLC, Rock Falls, IL
Contract Value: $267,034.20
Improvements: Culvert extensions by the contractor; slope modifications by Ogle County forces

Road Name: Montague Road and Meridian Road
Township: Maryland, Leaf River, Marion
Location: Rock City Road to Leaf River Road on Montague Road, Lindenwood Road to Weld Park Road on Meridian Road
Anticipated Start Date:
Late August, 2008
Anticipated Completion Date: Early fall, 2008
Contractor: Lovewell Fencing, Inc, Davenport, IA
Improvements: Guardrail repairs and replacement

Road Name: Mulford Road
Township: Monroe
Location: Lindenwood Road to the Winnebago County line
Start Date: July 16; Constructed under traffic
Competion Date: August 8, 2008
Contractor: Micro-Surfacing, Inc., St. Louis, Mo
Contract Value: $189,702.72
Improvements: Microsurfacing overlay

Road Name: Ridge Road
Township: Pine Creek, Mt Morris
Location: Pines Road to IL Route 64
Anticipated Start Date: August 14, 2008; constructed under traffic
Anticipated Completion Date: September 12, 2008
Contractor: Northwest Illinois Construction, LLC, Rock Falls, IL
Contract Value: $547,644.94
Improvements: Hot-mix asphalt overlay and shoulder improvements

Road Name: River Road & the Rock River Terrace
Township: Rockvale
Location: Devils Lane to Main Street on River Road & sideroads in the Rock River Terrace
Start Date: May 12, 2008; constructed under traffic
Anticipated Completion Date: August 15, 2008
Contractor: Rock Road Companies, Rockford, IL
Contract Value: $690,397.45
Improvements: Replacing curb & gutter and storm sewers; pavement resurfacing

Road Name: Half Mile Road & Silver Creek Road
Township: Rockvale
Location: River Road to Daysville Road on Half Mile Road; Mud Creek Road to West Grove Road on Silver Creek Road
Start Date: June 20, 2008; constructed under traffic
Completion Date: August 15, 2008
Contractor: U.C. Paving, Peru, IL
Contract Value: $274,039.30
Improvements: Hot-mix asphalt overlay

Last update: August 11, 2008